Construction Progress Update – Week Ending 04/21/17

CONSTRUCTION PROGRESS UPDATE WEEK ENDING APRIL 21, 2017 –    Stucco on High Roof complete, Balcony Stucco continues –    Drywall stud framing continued through the 17th floor –    Completed plastering on the ceilings of the 17th floor –    Completed top track installation done through 17th floor –    Fire riser main is up … Continue reading Construction Progress Update – Week Ending 04/21/17